Definitions of Civil
Engineering Terms
ABRASION: The process of wearing away by friction.
ABUTMENT: A
concrete support wall constructed at both ends of a bridge or an arch, in order
to resist the horizontal force from the bridge or the arch, support the ends of
the bridge span and to prevent the bank from sliding under.
ACCELERATOR: A substance such as calcium chloride (CaCl2),
added in small quantities (max. 0.03% of the cement) to plain concrete to
hasten its hardening rate, its set or both.
ACQUISITION: The process of obtaining Right-of-Way.
ACTIVE EARTH PRESSURE: The horizontal push from earth onto a wall. The
active earth force from sand on to a free retaining wall is equivalent to that
from a fluid of density 0.25 to 0.30 times that of the sand. The force from
sand on to a fixed retaining wall is very much more.
ADDENDUM OR
ADDENDA: Written instruments or
documents issued prior to the execution of a contract to modify or revise the
bidding documents.
ADHESION OR
BOND: The sticking together of
structural parts by mechanical or chemical bonding using a cement or glue.
ADMIXTURE OR ADDITIVE: A substance other than aggregate, cement or water, added
in small quantities to the concrete mix to alter its properties or those of the
hard concrete. The most important admixtures for concrete are accelerators,
air-entraining agents, plasticizers and retarders.
AFFIDAVIT OF NON-COLLUSION: A sworn statement, by bidders for the same work, that
their proposal prices were arrived at independently without consultation or a
secret agreement or cooperation for a fraudulent or deceitful purpose between
or among them.
AGENT: The person who legally represents the
contractor and acts for him on all occasions. He is often a Civil Engineer.
AIR-ENTRAINED CONCRETE: A concrete used for constructing roads. It has about 5%
air and is therefore less dense than ordinary good concrete, but it has
excellent freeze-thaw resistance. The strength loss is roughly 5% for each 1%
air entrained. Air entrained concrete produced by adding an admixture to
concrete or cement, which drags small bubbles of air (Smaller than 1 mm in
diameter) into the concrete mix. The bubbles increase the workability and
allowing both sand and water contents to be reduced.
ALIGNMENT:
(1) The fixing of points on the ground in the correct lines for setting out a
road, railway, wall, transmission line, canal, etc. (2) A ground plan showing a
route, as opposed to a profile or section, which shows levels and elevations.
APPURTENANCE: An item which belong with, or is designed to
complement something else (For example, a manhole is a sewer appurtenance.)
APRON: A floor constructed along the channel bottom
to prevent scour. Aprons are almost always extension of culverts.
AQUIFER: An underground source of water capable of
supplying a well.
ARITHMETIC
MEAN: The average value which
is defined as the sum of all of the observations divided by the number of
observations.
ARTESION WELL: A spring which water flows naturally out of
the earth's surface due to pressure placed on the water by an impervious
overburden and hydro-static head.
ARTERIAL HIGHWAY: A general term denoting a highway primarily
for through traffic usually on a continuous route.
AS-BUILT DRAWINGS OR RECORD DRAWINGS: Construction drawings revised to show
significant changes made during the construction process, usually based on
marked-up prints, drawings and other data furnished by the contractor or the
Engineer.
ASPHALTIC CONCRETE FRICTION COURSE (ACFC): A hot mixture of asphalt cement with an
open-graded aggregate (20% to 25% air voids) of a maximum size of 3/8 inch used
as a surface (Wearing) course.
ASPHALT
RUBBER (AR): A mixture of
asphalt cement and rubber used as a crack sealent, binder, or membrane.
ASPHALTIC CONCRETE (ASPHALT RUBBER): A hot mixture of asphalt cement, rubber, fine
and coarse aggregate and mineral admixture mixed together and placed as an
asphaltic concrete pavement surface layer. The advantages of this mix are: It
stops cracks from reflecting through pavement layers, reduce the riding tires
noise and is a useful way to dispose of the used rubber tires.
AUXILIARY LANE:
The portion of a roadway adjoining the traveled way for truck climbing, speed
change or for other purposes supplementary to through traffic movement.
(B)
BALLAST:Coarse stone or hard clinker, sand or slag
carried by a moving unit to keep it held down or to keep equilibrium steady.
BANK: A mass of soil rising above a digging level.
BASE COURSE:
One or more layers of specified materials of designed thickness (Usually
asphaltic concrete course), placed on a subbase course or a subgrade to support
a surface course.
BASEMENT
MATERIAL: The material in
excavation or embankment underlying the lowest layer of subbase, base,
pavement, surfacing or other specified layer which is to be placed on.
BASIN: A receptacle for runoff (Storm) water.
BATTER: Inward slope from bottom to top of a wall face.
BERM: An
artificial horizontal ledge in an earth bank or cutting to ensure the stability
of a steep side slopes of roadbed (Shoulder). Also berms are built to hold
water on land that is to be flood irrigated.
BEAM: A horizontal structural member designed to
resist loads which bend it.
of a beam length or area. (2) The compressive stress
between a beam and its support (bearing pressure), particularly on foundations.
(3) The horizontal angle turned between a datum direction such as true north
and a given line.
BENCH MARK: A relatively fixed point whose elevation is
known and used as a datum for leveling.
BENDING
FORMULA : Formula for beams of
any homogeneous material. Moment (M)= Stress X Modulus of Section or (M)= Force
X Arm
BERNOULLI
EQUATION: Is an Energy equation
for two points along the bottom of an open channel experiencing uniform flow.
P1 + V1 + Z1 + W
pump = P2 + V2 + Z2 + h + W turbine
2g 2g
BIDDER: Any
individual, firm, partnership, corporation, or combination thereof, submitting
a proposal for the work contemplated, acting directly or through a duly
authorized representative.
BINDER: (1)
A material such as cement, tar, bitumen, gypsum plaster, lime, or similar
material, when mixed with other material, it causes unifomity, consistency,
solidification or cohesion. (2) The clay or silt in hoggin or the cement rock.
(3) A stirrup or steel rod usually about 6 to 10 mm diameter used for holding
together the main steel in a reinforced-concrete beam or column.
BITUMINOUS
SEAL COAT: A thin bituminous
application to a surface or wearing course to seal and waterproof small voids
and to embed sand or chips to provide better traction.
BLEEDING or FLUSHING: (1) Separation of clear water from the cement paste of
mortar or concrete. Two types are known, the first beneficial, the second
harmful to concrete strength, but they may co-exist. The first occurs during
compaction, water can flow out of concrete, lie on its surface, and thus
encourage good curing for the first few hours during hot weather. The second
type of bleeding occurs after compaction, water segregates beside or under the
steel or larger stones, weakening the bond between them and the body of the
concrete. A plasticizer should enable the water to cement ratio to be lowered
to reduce this type of bleeding. (2) Upward migration of bituminous material
resulting in a film of asphalt on the surface.
BLEMISH: Any imperfection which mars the appearance of
wood, concrete, paint or other finished surface.
BLINDING:
Mat or mattress or sealing coat. A layer of lean concrete usually 2 to 4 inches
thick, put down on soil such as clay to seal it and provide a clean bed for
reinforcement to be laid on.
BLOTTER:Absorbant material (i.g., sand) to dry freshly
wet surfaces.
BORING: A drilling into the earth to bring up samples
of the soil.
BORROW: Suitable material excavated from sources
outside the roadway prism (i.g., Borrow Pit), to provide fill elsewhere,
primarily for embankment.
BOULDER: A rock which is too heavy to be lifted readily
by hand.
BOULEVARD: A wide city street usually planted with
shade-trees (Landscaped).
BRIDGE: A
single or multiple span structure, including supports, erected over a
depression or an obstruction such as water, a highway or railway and having a
track or passageway for carrying traffic.
BRIDGE
BEARING: The support at the
bridge pier or abutment, which carries the weight of a bridge.
BRIDGE DECK: The load-bearing floor of a bridge, that
carries and spreads the loads to the main beams.
BRIDGE
LENGTH: The greater dimension
of a structure measured along the center of the roadway between backs of
abutment backwalls or between ends of the bridge floor.
BRIDGE ROADWAY WIDTH: The clear width of structure measured at right
angles to the center of the roadway between the bottom of curbs or between the
inner faces of parapet or railing.
BYPASS: Road joining two parts of an older road to
avoid a town or village.
(C)
CALENDAR DAY: Any day shown on the calendar, and the 24-hour
period thereof from 12:01 a.m. to midnight.
CANTILEVER: A beam which is securely supported at one end,
and hangs freely at the other; an overhanging beam.
CAMBER: A slightly arched surface of a road to
compensate for anticipated deflection or to allow for drainage.
CANTILEVER
FOOTING: A combined footing
that supports an exterior wall or exterior columns.
CAPILLARY PRESSURE OR SEEPAGE FORCE: In ground which is being drained from outside
an excavation, capillary pressures help the excavated earth to stand steeply.
However, if the ground is being drained from inside and not from outside the
excavation, the capillary pressures will help the earth face to collapse.
CAPILLARY
WATER: Water just above the
water table which is drawn up out of an aquifer due to capillary action of the
soil.
CARRIAGEWAY: The part of a highway which carrier vehicles.
CASSION: A cylindrical or rectangular rigged-wall for
keeping water or soft ground from flowing into an excavation while digging for
foundations or piles.
CAST-IN-PLACE
or CAST-IN-SITU: Concrete
deposited in its permanent place.
CAULKING: Using pressure gun for filling of a crack,
crevice, seam or joint to make it air or water-tight.
CEMENT: A mixture of silicates and aluminates of
calcium that when mixed with water it binds a stone-sand mixture into a strong concrete
within a few days.
CEMENT
MORTAR: Mortar usually composed
of four parts sand to one of cement, with a suitable amount of water.
CENTER LINE OF HIGHWAY: A line equidistant from the edges of the median separating
the main traveled ways on a divided highway, or the center line of the main
traveled way on undivided highway.
CHANNEL: A natural or artificial water course.
CHAINAGE: A length (Usually 100 feet) measured by chain
or steel tape.
CHANGE ORDER: A written order issued by the Engineer to the Contractor, and signed by
both, which set forth any necessary or desirable changes in the contract
including, but not limited to, extra work, increases or decreases in contract
quantities, the basis of payment, contract time adjustments and other additions
or alteration to the contract. A change order signed by the Contractor
indicates his agreement therewith.
CHARACTERISTIC: A measurable property of a material, product or
item of construction.
CHEVRON: V shaped strips meeting at an angle.
CHEZY-MANNING
EQUATION: Used to measure water
flow in open channels.
Q = V A = 1.49
(A) (rH) S =n
CHROMATING: Priming with lead or zinc to prevent forming of
rust.
CLAY: Very
fine-grained soil of colloid size(Finer than 0.002 mm), consisting mainly of
hydrated silicate of aluminum. It is a plastic cohesive soil which shrinks on
drying, expands on wetting, and gives up water when compressed.
COARSE AGGREGATE: (1) For concrete: aggregate which retained on the No. 4
sieve (4.76 mm). (2) For bituminous material: aggregate which retained on a
sieve of 3 mm square opening.
COBBLE: Rock fragments between 3 to 6 in size.
COHESION OF
SOIL: The stickiness of clay or
silt. It is the shear strength of clay, which generally equals about half its
unconfined compressive strength.
COHESIVE SOIL: A sticky soil like clay or clayey silt.
COHESIONLESS
SOIL: Sand, gravel and similar
soils, also known as frictional soils since their properties are defined more
by their angle of internal friction than by cohesion.
COMPACTION:
Artificial increase of the dry density of a granular soil by mechanical means
such as rolling the surface layers, or driving sand piles for deep compaction,
vibroflotation, or impact methods. There are many methods of compaction, six
main types of compacting equipment are: (1) pneumatic-tyred rollers, in which
the rear wheels cover the gaps left by the front wheels, (2) tamping rollers,
(3) sheepsfoot rollers, (4) vibrating rollers, (5) frog rammers (trench
compactors), and (6) vibrating plates. The last two are used for confined
spaces.
COMPOUND: A homogeneous substance composed of two or more
elements that can be decomposed by chemical changes only.
CONCRETE: A mixture of water, sand, stone, and a binder
(Usually portland cement) which hardens to a stonelike mass. There are four
types of portland cement:
Type I: Normal portland cement: This is a general-purpose cement
used whenever sulfate hazards are absent and when the heat of hydration will
not produce objectionable rises in temperature. Typical uses are sidewalks,
pavement, beams, columns and culverts.
Type II: Modified portland cement (Sulfate-resistant portland
cement): This type of cement is applicable when exposure to severe sulfate
concentration is expected, generally used in hot weather in the construction of
large concrete structures. Its heat rate and total heat generation are lower
than for normal portland cement.
Type III: High-early strength portland cement: This type develops
its strength quickly. It is suitable for use when the structure must be put
into early use or when long-term protection against cold temperatures is not
feasible. Its shrinkage rate, however, is higher than for types I and II, and
extensive cracking may result.
Type IV: Low-heat portland cement: For extensive concrete structures,
such as gravity dams, low-heat cement is required to minimize the curing heat.
The ultimate strength also develops more slowly than for the other types.
CONDUIT: Any open channel, pipe, etc., for flowing
fluid. A pipe or tube in which smaller pipes, tubes, or electrical conductors
are inserted or are to be inserted.
CONSISTENCY
OF CONCRETE: Ease of flow or
workability of concrete, measured by slump test or Kelly ball test.
The gradual, slow compression of a cohesive soil due to weight acting on
it, which occurs as water, or water and air are driven out of the voids in the
soil. Consolidation only occurs with clays or other soils of low permeability,
it is not the same as compaction, which is a mechanical, immediate process and
only occurs in soils CONSOLIDATION: with at least some sand.
CONTINUOUS
BEAM: A beam extending over
several spans in the same straight line.
CONTINUOUS or
COMBINED FOOTING: A long
footing supporting a continuous wall or two or more columns in a row.
CONTRACTOR: The person or persons, firm, partnership,
corporation, or combination thereof, private or municipal, who have entered
into a contract with the State (Client).
CONTRACT:
The written agreement between the State (Client) and the contractor setting
forth the obligation of the parties thereunder, including, but not limited to,
the performance of the work, the furnishing of labor, equipments and materials
and the basis of payment. The contract includes the Advertisement for Bids,
Proposal, Bidding Schedule, Contract Agreement and Contract Bonds, Certificate
of Insurance, Standard Specifications, Supplemental Specifications, Special
Provisions, Project Plans, Standard Drawings and any Supplemental Agreements
that are required to complete the construction of the work in an acceptable
manner within a specified period, including authorized extensions thereof, all
of which constitute one instrument.
CONTRACT PAYMENT BOND: The approved form of security, executed by the Contractor
and his surety or sureties, guaranteeing complete performance of the contract
and all supplemental agreements pertaining thereto and the payment of all legal
debts pertaining to the construction of the project.
COPING: The cap or top course of a wall.
CORROSION: Disintegration or deterioration of metal,
concrete or reinforcement by electrolysis or chemical attack.
CORRUGATIONS: Regular transverse undulation or alternate
ridges upon a metal pipe surface to give greater rigidity to thin plates.
COURSE: The roadway horizontal pavement layer.
CRITERIA: The Client's requirements for the design and
construction of a particular type of building, or structure.
CRITICAL:
(1) Of, relating to, or being a turning point or specially important juncture.
(2) Relating to or being a state in which a measurement or point at which some
quality, property or phenomenon suffers a definite change.
CRACKING IN CONCRETE: Cracking is always expected in reinforced concrete, since
it has such a high shrinkage on hardening. Additional cracks will occur on the
stretched side of a beam. Reinforcement shall be inserted sufficient in
quantity and closeness to make the cracks invisible to the naked eye and very
close together. Contraction and expansion joints are constructed to reduce
cracking.
CRACK: An open seam not necessarily extending through
the body of a material. Some types of cracks in asphaltic or portland cement
concrete are:
(1) ALLIGATOR CRACK: A crack caused by fatigue of the asphaltic concrete
surface layer or excessive movement of the underlying layers. Typically alligator
cracks form an interconnected network of irregularly shaped polygons varying in
size from a few square inches to 1 square foot.
(2) BLOCK CRACK: A crack caused by shrinkage of the bound surface material.
Typically block cracks form an interconnected network of nearly square shapes
varying in size from 1 square foot to several square feet.
(3) DURABILITY (D) CRACK: A series of closely-spaced cracks adjacent and roughly
parallel to concrete pavement joints. caused by the freezing and thawing of
unsound aggregates that have a high moisture content.
(4) RANDOM CRACK: A crack that is neither longitudinal or transverse crack
and that has a little or no interconnection with other cracks. May be caused by
movement, either of the pavement structure or subgrade or both.
(5)
REFLECTIVE CRACK: Crack in a
pavement surface layer caused by the high
stresses from
movements of a cracked underlying layer.
(6) TRANSVERSE OR TEMPERATURE CRACK: A long crack approximately perpendicular to the
centerline caused by longitudinal shortening of the bound surface layer,
sometimes called temperature cracks as the shortening is often caused by
contraction from temperature changes. Typically transverse cracks extend across
the full width of the pavement.
(7) CRAZE CRACK: Numerous fine cracks which appear on the surface of
concrete in a hexagonal or octagonal pattern. This type of crack is caused by
improperly trowelled concrete surface.
CULVERT: A covered channel up to about 12 feet in width
or a large pipe for carrying a watercourse below ground level, usually under a
road or railway.
CURING:
Keeping freshly poured concrete or mortar damp for specified time (Usually the
first one week of its life) so that the cement is always provided with enough
water to harden. This improves the final strength of concrete, particularly at
the surface, and should reduce surface cracking or dusting.
(D)
DADO: Concrete barrier on the sides of bridge approach
slab; the part of pedestal between cap and base.
DATUM: Any elevation taken as a reference point for
leveling.
DECK: (1) A flat roof, a quay, jetty or bridge floor,
generally a floor form with no roof over upon which concrete for a slab is
placed. (2) Formwork for a level surfaces.
DEFORMED BAR: A reinforcing bar with ridges to increase
bonding between the reinforcing bar and concrete.
DENSITY INDEX (relative density): is a measure of the tendency or ability to
compact soil during loading. The density index is equal to 1 for a very dense
soil; it is equal to 0 for a very loose soil.
DETOUR: A temporary route for traffic around a closed
portion of a road.
DEVIATION: Difference between the value and the average of
a set.
DIAPHRAGM: (1) A stiffening plate in a bridge between the
main girders in a bridge or a stiffening web across a hollow building block.
(2) Legamentous wall separating two cavities.
DILUTION: Reducing a concentration of soluble material by
adding pure water.
DISTILLATION: Salt removal process from brackish or sea water
by boiling and condensation.
DITCH: Long narrow excavation for drainage, irrigation
or burying underground pipelines.
DIVIDED
HIGHWAY: A highway with
separated traveled ways for traffic, generally in opposite directions.
DREDGE: To dig or excavate under water.
DUCT: A protective tube or a brick or concrete trench
or corridor along which pipes or cables pass through the ground.
DUCTILITY: The ability of a metal to undergo cold plastic
deformation without breaking, particularly by pulling in cold drawing.
DURABILITY: The ability of materials to resist weathering
action, chemical attack, abrasion or other conditions of service.
DYKE: (1) A mound of earth along a river or channel
bank to retain floodwater. (2) large ditch. (3) A tabular-shaped igneous
intrusion.
(E)
EASEMENT: The right to use or control the property of
another for designated purposes.
ECCENTRIC LOAD: A load on a column applied at a point away from the column
center and therefore putting a bending movement on the column equal in amount
to the load multiplied by the arm.
EFFICIENCY: It is the power output divided by the power
input.
ELASTOMER: Elastic rubber like substance, neoprene, etc.
EMBANKMENT: A ridge of earth or rock placed, shaped and
compacted to carry a road, railway, canal, etc., or to contain water.
EMPIRICAL
FORMULA: A formula or rule
based on one or many series of observations or trials, but with no theoretical
calculation.
EMULSION: A
mixture with water. Asphalt emulsions are produced by adding a small amount of
emulsifying soap to asphalt cement and water. When the water evaporates, the
asphalt sets.
ENCROACHMENT: The use of the highway right-of-way for
nonhighway structures or other purposes.
ENERGY: A
capacity for doing work, expressed in work units. Energy may be inherent in the
speed of a body (Kinetic energy) or in its position relative to another body
(Potential energy).
ENGINEER:
The State (Client) representative Engineer, acting by and under the authority
of the laws of the State (Client). The Engineer is responsible for the
Engineering monitoring and checking of construction work progress and
conformance to the project specifications requirements.
ENGINEERING: The science through which the properties of
matter and the sources of power are utilized for man's benefit.
EPOXIDE, EPOXY, ETHOXYLENE RESIN: A synthetic, usually two-part material that can
set and harden under water or be used for bonding roof bolts or for repairing
concrete in heavily trafficked areas, etc.
EROSION: Wearing or scouring caused by the abrasive
action of moving water or wind.
ERRATIC: Values which seem to vary excessively from the
average.
ERROR: A difference from an average value. An
unintentional deviation from correct value.
EXPANSION OR
CONTRACTION JOINT: A gap or
space in the steel or the concrete to accommodate both thermal expansion and
contraction.
EXPRESSWAY: A divided arterial highway for through traffic
with full or partial control of access.
EXTRAPOLATE: To project tested values, assuming a continuity
of an established pattern.
EXTRA WORK:
Additional construction work for which no price or compensation is provided for
in the contract and for which the Contractor is not deemed liable under any
other provision of the contract, but found by the Engineer to be necessary or
desirable for the satisfactory completion of the contract.
EXTRUSION: Forming rods, tubes, or sections of specified
shape by pushing hot or cold metal or plastics through a shaped die to the
required section.
(F)
FACTOR OF
SAFETY: The stress at which
failure is expected, divided by the design stress (maximum permissible stress).
FALSEWORK: Support for concrete formwork or for an arch
during construction.
FATIGUE: The lowering of the breaking-load of a member
by repeated reversals of stress so that the member fails at a much lower stress
than it can withstand under static loading.
FAULTING:
The difference in elevation of two adjacent concrete slabs at a joint,
primarily caused by the traffic-induced movement of base material particles
from under one joint edge to under the adjacent joint edge.
FILL: Earthwork
in embankment or backfilling.
FILLET: 3 to 6 inches wide shamfer for column to add
beauty and strength by avoiding sharp angels.
FILLET WELD: A weld of roughly triangular cross-section
between two pieces at right angles.
FINE AGGREGATE: (1) Sand or grit for concrete which passes the No. 4 sieve
(4.76 mm) and retained in the No. 200 sieve (74 micron or 0.074 mm). (2) Sand
or grit for bituminous road-making which passes a sieve of 3 mm square opening.
FIXED COSTS:
Any necessary labor, material and equipment costs, directly expended on the
item or items under consideration which remain constant regardless of the
quantity of the work done.
FLAKING: Peeling off of the coating.
FLEXIBLE PAVEMENT: An asphaltic pavement structure having sufficiently low
bending resistance to maintain intimate contact with the underlying structure,
yet having the required stability furnished by aggregate interlock, internal
friction between particles and cohesion to support traffic.
FLEXURE: Word meaning bending.
FLUME: A wooden, steel or concrete open channel to
carry or measure water flows.
FLY-ASH: The ash which goes to the chimney from
pulverized coal and is caught in the flue- gas dust extractors. It is used as
pozzolan or as an admixture to cement.
FORCE: That which tends to accelerate a body or change
its movement (i.g., the weight of a body is a force which tends to move it
downwards).
FORMATION
LEVEL: The surface level or
elevation of the ground surface after all digging and filling, but before
concreting.
FORMWORK: The wood molds used to hold concrete during the
placement and curing processes.
FOUNDATION
FAILURE: Foundations of
buildings can fail in one of two ways, first by differential settlement,
secondly by shear failure of the soil.
FREEWAY: A divided arterial highway with full control of
access.
FRICTIONAL SOIL: A clean silt, sand or gravel that is a soil whose shearing
strength is mainly decided by the friction between particles. In Coulomb's
equation, sand shear strength is given by the statement S = P tan O, since sand
has no cohesion.
FRONTAGE
ROAD: A local street or road
auxiliary to, and located on the side of an arterial highway for service to an
abutting property and adjacent areas, and for control of access.
FROST:
Weather during which dew is deposited as ice. The danger to construction caused
by frost is that water expands by about 9% of its volume when it freezes.
Therefore concrete or mortar which have not set and contain free water are
disintegrated by it.
FUSION WELDING: The welding of metals or plastics by any method which
involves melting of the edges of the parts to be joined without pressure.
Usually a filler rod provides the weld metal.
(G)
GABIONS:
Compartmented rectangular containers made of galvanized hexagonal steel wire
mesh and filled with stone. Gabions are used to stabilize and protect embankment
slopes from erosion.
GANTRY: (1) A temporary staging for carrying heavy
loads, such as earth. (2) overhead structure that supports signs, usually built
of square timbers or steel joists.
GEOSYNTHETICS (GEOMATRIX, GEOMEMBRANE AND GEOTEXTILE): Thin fabrics membranes and composites placed
between soil layers to prevent sliding and for reinforcing or to retard the
migration of clay into the pavement structure or placed between pavement layers
for reinforcing or to retard crack propagation from an underlying layer to the
one above it.
GIRDER: A large beam, usually of steel or concrete. Its
chords are parallel or nearly so, unlike a truss.
GORE: The V (Triangular) shaped area immediately
beyond the divergence of two roadways bounded by the edges of those roadways.
GRANULAR: Material that does not contain more than 35
percent of soil particles which will pass a No. 200 sieve.
GRADING: Shaping and leveling the ground surface,
usually by earth-moving equipments such as graders.
GRADIENT OR GRADE: The rise or fall per unit horizontal length (Slope) of a
pipe, road, railway, flume, etc. Slope also expressed as the number of degrees
from the horizontal or as a percentage.
GRAVEL:
Granular material retained on a No. 4 sieve (4.76 mm) which is the result of
natural disintegration of rock, or untreated or only slightly washed, rounded,
natural aggregate, larger than 5 mm.
GRID: Any rectangular layout of straight lines
(Generally used in locating points on a plan).
GRILLAGE: A footing or part of a footing consisting of
horizontally laid timbers or steel beams.
GROOVING: The process of producing grooves in a concrete
pavement surface to improve frictional characteristics.
GROUNDWATER: Water contained in the soil or rocks below the
water table. Water table if lowered too much, the ground may settle
disastrously.
GROUNDWATER LOWERING: Lowering the level of groundwater is to ensure a dry
excavation in sand or gravel or to enable the sides of the excavation to stand
up. Groundwater lowering in this sense is always carried out from outside the
excavation either by well-points or from filter wells.
GROUT: (1)
To fill with grout. (2) Fluid or semi-fluid cement slurry or a slurry made with
other materials for pouring into the joints of brickwork or masonry or for
injection into the ground or prestressing ducts. Grouting of ducts improves the
bond and may reduce corrosion of the tendons but it prevents their inspection
and re-tensioning or renewal.
GUNITE, SHOTCRETE: A cement-sand mortar, thrown on to formwork or walls or
rock by a compressed-air ejector, which forms a very dense, high-strength
concrete. It is used for repairing concrete surfaces, making the circular walls
of preload tanks, protecting wearing surfaces of coal bunkers; covering the
walls of mine airways or water tunnels, stabilizing earth excavation slopes and
so on.
GULLEY: (1)
A pit in the gutter by the side of a road. It is covered with a grating. (2) A
small grating and inlet to a drain to receive rainwater and wastewater from
sinks, baths or basins.
(H)
HEAVE: Upward
movement of soil caused by expansion or displacement resulting from phenomena
such as moisture absorption, removal of overburden, driving of piles, frost
action, etc.
HEDGE: A row of closely planted shrubs forming a
fence.
HIGHWAY: The whole right of way or area which is
reserved and secured for use in constructing the roadway and its appurtenances.
HONEYCOMBING:
Local voids or roughness of the face of a concrete structure, caused by the
concrete having segregated so badly that there is very little sand to fill the
gaps between the stones at this point. Such concrete is weak and should be cut
out in a rectangular or square shapes and rebuilt if the wall is heavily
loaded.
HYDRATION:
The combination of water with any substance such as lime or minerals, which is
responsible for the alteration of minerals in weathering; the formation of
hydrated lime; the setting of cement and so on.
HVEEM'S RESISTANCE VALUE TEST (The R-Value): The R-value is a measure of the ability of a
soil to resist lateral deformation when a vertical load acts upon it. The
R-value ranges from zero (the resistance of water) to 100 (the approximate
resistance of steel). R- values of soil and aggregate usually range from 5 to
85.
(I)
IMPERVIOUS:
Resistant to movement of water; a description of relatively waterproof soils
such as clays through which water percolates at about one millionth of the
speed with which it passes through gravel.
INITIAL
SETTING TIME: The time required
before a concrete mix can carry a small load without sinking like a mud. This
is after about one hour in warm weather.
INHERENT SETTLEMENT: The sinking of a foundation due only to the loads which it
puts on the soil below it and not to the loads on any nearby foundations. In
city sites where the foundations are on clay, all foundations suffer both
inherent and interference settlement.
INTERFERENCE
SETTLEMENT: The sinking of a
foundation due to loads on foundations near it and the natural extension of
their settlement craters beyond their own boundaries.
INTERPOLATION: (1) Inferring the position of a point between known points on a graph
by assuming that the variation between them is smooth. Usually the assumption
is that the variation is linear (A straight-line variation). (2) To estimate
untested values which fall between tested values.
INVERT LEVEL: The level of the lowest part of a pipe invert.
(J)
JOINT
SEALANT: A material used as a
filler in concrete pavement joints to prevent infiltration of water, soil and
other fine particles.
JOIST: A horizontal wooden, steel or precast concrete
beam directly supporting a floor.
(K)
KEYWAY: A recess or groove in one lift or placement of
concrete which is filled with concrete of the next lift, giving shear strength
to the joint, also called a key.
KINETIC ENERGY:
The energy of a moving body due to its mass and motion.
K.E.= W x V / 2
g.
(L)
LAITANCE: A
layer of weak and non-durable cement concrete caused by bleeding as a result of
excessive vibration of concrete or over trowelling the mortar. It is weaker
than the rest of the concrete and should be cut away and covered with a pure
cement wash before laying more concrete on it.
LANDSLIP OR LANDSLIDE: A sliding down of the soil on a slope because of an
increase of loading (Due to rain, new building, etc.), or a removal of support
at the foot due to cutting a railway or road or canal. Clays are particularly
liable to slips.
LEAN CONCRETE BASE (LCB): A mixture of aggregate, cement and water used directly
under concrete pavement. The mixture has a lower modulus of rapture than the
concrete pavement, and a higher compressive strength than cement treated base.
LEDGE: A horizontal projection or cut forming a shelf,
cliff or rock wall.
LIME: Calcium
oxide (CaO).
LIQUID LIMIT: The moisture content at the point between the
liquid and the plastic states of a clay.
LIQUIDATED DAMAGES: The amount prescribed in the contract specifications, to be
paid to the State (Client) or to be deducted from any payments due or to become
due the Contractor, for each day's delay in completing the whole or any
specified portion of the work beyond the time allowed in the contract
specifications.
LLOYD DAVIES FORMULA: A method for calculating the run-off, from which the sizes
of sewers are calculated (Runoff water in cubic feet = 60.5 X area drained in
acres X rainfall in inches per hour X impermeability factor).
LOESS: Deposit of very porous and cavitated wind-blown
silt and clay.
LONG COLUMN:
A column which fails when overloaded, by buckling rather than by crushing. In
reinforced-concrete work this is assumed to happen when columns which are
longer than fifteen times their least dimension.
LONGITUDINAL
JOINT: A joint normally placed
between traffic lanes in rigid pavements to control longitudinal cracking.
LOSS OF
PRESTRESS: Losses of
prestressing force after transfer arise mainly through elastic shortening,
shrinkage and creep of the concrete and creep of the steel.
LOT: An isolated quantity of material from a single
source.
LUMINAIRE: Complete lighting device for the highway.
(M)
MARSHES: Low lying wet land; swamp.
MATERIALS: Any substance specified for use in the
construction of the project and its appurtenances.
MAXIMUM DRY
DENSITY: The dry density
obtained by a stated amount of compaction of a soil at the optimum moisture
content.
MEAN: An
arithmetic mean is an average in which all signs are taken as positive. In an
algebraic mean the signs of the quantities are considered and the mean may be
either positive or negative.
MEDIAN: That portion of a divided highway separating
the traveled ways for traffic in opposite directions including inside
shoulders.
MEMBRANE: A thin film or skin, such as the skin of a soap
bubble or a waterproof skin.
MILLING:
(1) Removing a specified thickness of an existing pavement surface by grinding
with a milling machine. (2) Removing metal shavings from a surface by pushing
it on a moving table past a rotating toothed cutter.
MIST: Very thin fog.
MOISTURE
CONTENT: The weight of water in
a soil mass divided by the dry weight of the solids and multiplied by 100.
MOMENT
CARRYING ABILITY OF REINFORCED CONCRETE BEAM (Nominal Strength, Mn):
Mn = Ast. fy [d
- 0.59 Ast. fy] or Mn = bd2 fy [1 - 0.59 fy]
[ fc'b ] [ fc' ]
MONOLITHIC
CONSTRUCTION: Constructed as one piece.
MORTAR: A paste of cement, sand and water laid between
bricks, blocks or stones.
MOVEMENT JOINTS IN CONCRETE: Movement joints may be of five types,
though it is possible for one to combine the properties of one or more others.
They reduce or prevent cracking or buckling caused by temperature changes,
shrinkage, creep, subsidence and so on. Their location is important. Where
possible, they should be placed at points where cracking (or buckling) might
start. The five types of joints are: contraction, expansion, hinge or hinged
joint, settlement and sliding joints.
MULCH: Mixes of wet straw and leaf peat.
MUNICIPALITY: City, town or county.
(N)
NEGATIVE MOMENT:A condition of flexture (Bending) in which top fibers of a
horizontally placed member (Beam), or external fibers of a vertically placed
exterior member (Column), are subjected to tensile stresses.
NEOPRENE: Synthetic rubber resistant to chemical
compound, oil, light, etc.
NEUTRAL SURFACE: In a beam bent downwards, the line or surface of zero
stress, below which all fibres are stressed in tension and above which they are
compressed. The neutral axis passes through the center of area of the section
(Centroid), if it is of homogeneous material.
(O)
OFFSET: A horizontal distance measured at right angles
to a survey line to locate a point off an edge line.
OPTIMUM MOISTURE CONTENT: That moisture content of a soil at which a precise amount
of compaction produces the highest dry density. It is particularly important to
achieve this in soil stabilization before the road is completed. It is the
percentage of moisture at which the greatest density of a particular soil can
be obtained through compaction by a specified method.
OVERBURDEN: Material of inferior quality which overlies
material of desired quality and which must be removed to obtain the desired
material quality.
OVERLAY: One or more courses of asphaltic concrete
layers placed over existing worn or cracked pavement.
(P)
PARAPET: Any protective railing, low wall or barrier at
the edge of a bridge, roof, balcony or the like.
PARKWAY: An arterial highway for non-commercial traffic,
with full or partial control of access, usually located within a park or a
ribbon of parklike development.
PASSIVE
PRESSURE: A pressure acting to
counteract active pressure.
PAVEMENT: The uppermost layer of material placed on the
traveled way or shoulders. This term is used interchangeably with surfacing.
PAVEMENT
STRUCTURE: The combination of
subbase, base course, and surface course placed on a subgrade to support the
traffic load and distribute it to the subgrade.
PEAT: Plant material partly decomposed by action of
water.
PEBBLES: Smaller pieces of material (0.12 to 0.25 inch
minimum size) which have broken away from a bedrock..
PEDESTAL: An upright compression member whose height does
not exceed three times its average least lateral dimension.
PERFORATED: Pierced with holes.
PERMEABILITY: That property of a material which permits a
liquid to flow through its pores or interstices.
An index of the acidity or alkalinity of a soil in terms of longarithm
of the reciprocal pH VALUE: of hydrogen ion concentration (e.g., a pH
indication of less than 7.0 is acidic, whereas a reading of more than 7.0 is
alkaline).
PIER: A wide column or a wall of masonry, plain or
reinforced concrete for carrying heavy loads, such as a support for a bridge.
PIER CAP: The top part of a bridge pier which uniformly
distribute the concentrated loads from the bridge over the pier .
PIER SHAFT: The part of a pier structure which is supported
by the pier foundation.
PILE: A long slender timber, concrete, or steel
structural element, driven, jetted, or otherwise embedded on end in the ground
for the purpose of supporting a load or compacting the soil.
PIT: Any borrow pit, mine, quarry or surface
excavation to obtain sand, clay, gravel, etc.
PLANS: The
official project plans and Standard Plans, profiles, typical cross sections,
cross sections, working drawings and supplemental drawings, or reproductions
thereof, approved by the Engineer, which show the location, character, dimensions
and details of the work to be performed. All such documents are to be
considered as a part of the plans, whether or not reproduced in the special
provisions.
PLASTICITY: The property of a soil which allows it to be
deformed beyond the point of elastic recovery without cracking or appreciable
volume change.
PLASTICITY
INDEX (PI): Numerical
difference between the liquid limit and the plastic limit. This is an
indication of the clay content on a soil or aggregate.
PLASTICIZER OR WATER REDUCER: An admixture in mortar or concrete which can increase the
workability of a mix so much, that the water content can be low and the mortar
or concrete strength can thus be increased.
PLASTIC LIMIT: The water content at the lower limit of the plastic state of a clay. It
is the minimum water content at which a soil can be rolled into a thread of 1/8
inch diameter without crumbling.
PLAT: A small
plot of land.
PORTLAND
CEMENT: A product obtained by
pulverizing clinker consisting mainly of hydraulic calcium silicates. Many
different cements now use portland cements or at least contain some, the
varieties include: Ordinary, Rapid-hardening, Ultra-high-early- strength,
Portland blast-furnace, Sulphate-resisting and Water- repellent cements, apart
from Colored cements.
POST-TENSIONING: A method of prestressing concrete in which the cables are
pulled or the concrete is jacked up after it has been placed. This method is
usual for bridges and heavy structures which are placed in place.
POTABLE
WATER: Drinking water.
POTENTIAL
ENERGY: Energy due to position
such as the elevation head of water or the elastic energy of a spring or
structure caused by its deformation.
PRECISION: Of a measurement, the fineness with which it
has been read, therefore, precision is different from accuracy.
PRECAST CONCRETE: Concrete beams, columns, lintels, piles, manholes, and
parts of walls and floors which are cast and partly matured on the site or in a
factory before being placed in their final position in a structure. Where many
of the same unit are required, precasting may be more economical than casting
in place, may give a better surface finish, reduce shrinkage of the concrete on
the site and make stronger concrete.
PRESSURE:A force acting on a unit area.
PRESTRESSING:
A process of preparing concrete slabs and beams for extra strength by placing
the mix over tightly-drawn special steel wire rope or rods which are later
released to provide strong dense concrete. prestressing accomplished by
applying forces to a structure to deform it in such a way that it will
withstand its working loads more effectively or with less total deflection.
When concrete beams are prestressed they deflect upwards slightly by an amount
about equal to their total downward deflection under design load. Downward
deflection is thus less that half that of a reinforced-concrete beam of the
same shape. The struts or braces to deep excavations in bad ground are
prestressed to prevent settlement of the surface and damage to neighboring
structures.
PRESTRESSED CONCRETE: Concrete in which cracking and tensile forces are
eliminated or greatly reduced by compressing it by stretched cables, wires or
bars within it. Two main methods for prestressingare : post-tensioning and
pre-tensioning. Prestressed concrete is economical for spans which are large or
where the beam depth must be reduced to a minimum.
PRIME COAT:
The initial application of a low viscosity bituminous material to an absorbent
surface, preparatory to any subsequent treatment, for the purpose of hardening
or toughening the surface and promoting adhesion between it and the
superimposed constructed layer.
PROFILE GRADE: The trace of a vertical plane intersecting the top surface of the proposed
wearing surface, usually along the longitudinal centerline of the roadbed.
Profile grade means either elevation or gradient of such trace according to the
context.
PROFILOGRAPH:
An instrument for measuring smoothness of a surface (as of metal casting, or a
highway or road) by amplification of the minute variations from the plane or
arc of smoothness.
PROJECT: The specific section of the highway together
with all construction to be performed thereon under the contract.
PROPOSAL: The offer of a bidder, on the prescribed forms,
to perform the work and to furnish the labor, equipments and materials at the
prices quoted.
(Q)
QUARRY: An open pit from which building stone, sand,
gravel, mineral, or fill, can be obtained.
(R)
RAMP: (1) A
steeply sloping road or floor. (2) A connecting roadway between two
intersecting highways at a highway separation (3) A short length of drain laid
much more steeply than the usual gradient.
RANDOM
SAMPLE: A sample selected
without bias so that each part has an equal chance of inclusion.
RANKINE THEORY: For dry, cohesionless backfill soil behind retaining
walls, the Rankine theory is used to find the vertical and the horizontal
(lateral) pressure at any depth, H. The horizontal pressure depends on 0.4 to
0.5 for untamped sand.
the coefficient
of earth pressure at rest,
, which varies
from
RAPID-HARDENING or HIGH-EARLY-STRENGTH CEMENT: A portland cement which hardens more quickly
than ordinary Portland cement and is more costly because it is more finely
ground.
RAVELLING OR
FRETTING: Progressive
disintegration of a pavement surface through the loss (Breaking away) of
aggregate particles from a road surface.
RAVINE: Deep,
narrow cliff or gorge in the earth surface.
RECYCLING
(PAVEMENT): The re-use of
existing pavement materials in a new pavement structure.
REHABILITATION: The improvement of an existing roadway surface by
improving the existing surface or by removing (milling) a specified thickness
of the existing pavement and placement of additional pavement layers.
RELEASE AGENT OR PARTING AGENT OR PARTING COMPOUND: A general term that includes any greases, mould
oils or sealants, laid over forms or form linings either to ensure a good
finish to the concrete, to prevent concrete bonding to forms or to improve the
durability of the form or for both.
REINFORCED CONCRETE: Concrete containing more than 0.6% by volume of
reinforcement consisting of steel rods or mesh. The steel takes all the tensile
stresses (theoretically). In good design the reinforcement is sufficiently
distributed so that the cracks are not conspicuous.
RESISTIVITY:
A measure of a substance's resistance to the flow of electricity through it,
expressed in ohm-centimeters. Used on soils to determine coating requirements
for new pipe and used to determine the extent of corrosion of existing metal
pipes.
RETARDER OR
RETARDER OF SET: An admixture
which slows up the setting rate of concrete.
RIGID
PAVEMENT: A pavement having
sufficiently high bending resistance to distribute loads over a comparatively
large area (Portland Cement Concrete Pavement).
RIGHT-OF-WAY: A general term denoting land, property of
interest therein, usually in a strip, acquired for or devoted to transportation
purposes.
RIDGE: A long narrow elevation of land.
RIGIDITY: Resistance to twisting or shearing.
RIPRAP: Rock used for the protection of embankments,
cut slopes, etc., against agents of erosion, primarily water.
ROADBED:
The roadbed is that area between the intersection of the upper surface of the
roadway and the side slopes or curb lines. The roadbed rises in elevation as
each increment or layer of subbase, base, surfacing or pavement is placed.
Where the medians are so wide as to include areas of undisturbed land, a
divided highway is considered as including two separate roadbeds.
ROADSIDE: A
general term denoting the area adjoining the outer edge of the roadway.
Extensive areas between the roadways of a divided highway may also be
considered roadside.
ROADWAY: That
portion of the highway included between the outside lines of sidewalks, or
curbs, slopes, ditches, channels, waterways and including all the appertaining
structures and other features necessary to proper drainage and protection.
RUMBLE STRIP, SERRATED STRIP OR JIGGLE BAR: A slightly raisedor lowered strip of asphalt,
plastic, etc., across the highway traffic lane or along the shoulder lane.
Rumple strips are placed together at a spacing (usually one foot) to warn the
driver, through an audible warning of the approaching hazard.
RUN-OFF: The
amount of water from rain, snow, etc., which flows from a catchment area past a
given point over a certain period. It is the rainfall less infiltration and
evaporation. it can be increased by springs of goundwater or reduced by loss to
the ground.
RUSTICATION: Having the surface rough or irregular, or the
joints deeply sunk or chamfered.
RUTTING: Formation of longitudinal depressions by the
displacement of soils or surfaces under traffic.
(S)
SAGGING
MOMENT: A bending moment which
causes a beam to sink in the middle. Usually described as a positive moment.
SAND:Grandular material passing through a #4 sieve
(4.76 mm), but predominantly retained above the No. #200 sieve (74 micron).
SAND
EQUIVALENT: A measure of the
amount of clay contamination in fine aggregate.
SATURATED
SURFACE DRY (SSD): A condition
of an aggregate which holds as much water as it can without having any free
surface water between the aggregate particles.
SCALING: A delamination of a thin portion of the top of
portland. cement concrete.
SCARIFIER, RIPPER OR ROOTER: An implement which may be self-propelled or towed behind a
tractor, with downward projecting tines for breaking a road surface for
approximately two feet deep or less.
SCOUR OR
EROSION: Removal of the sea bed
or of a river bed or banks by erosive action of waves or flowing water.
SCREED, SCREED BOARD, SCREED RAIL OR TAMPER: (1) A wood or metal templet with which a
concrete surface is finished. Screeds are set to the correct level for the slab
surface. The screed rail may be cambered but is usually straight. (2) A layer
of mortar 2 to 7 cm thick, laid to finish a floor surface or as a bed for floor
tiles.
SEALANT OR SEALING COMPOUND: (1) A fluid of plastic consistency laid over a joint
surface or the outside of a joint filler to exclude water. Hot bitumen, rubber
strip, plastic strip, hessian caulking, synthetic resins and building mastics
are used as sealant. (2) A durable coating of plastics such as epoxy resin or
polyurethane, painted on the face of form lining or timber formwork to enable
it to be reused many times. (3) Liquid-membrane curing compound. A coating for
roads (e.g., bituminous emulsion) over a damp, recently cast concrete surface,
which prevents loss of water, and thus ensures proper curing of the concrete.
(4) A treatmemt for a set concrete floor which strengthens the concrete surface
or binds the aggregate, ensuring that it does not dust. Sodium silicate
solution has been successfully used for many years.
SEDIMENT: Any material, mineral or organic matter
deposited by water, air, etc., often called silt.
SEPTIC-TANK: Underground sewage collecting tank.
SETTLEMENT OR SUBSIDENCE: Downward movement of a structure such as a railway bridge,
dam, or building, due to compression or downward movement of soil below it. It
need not be harmful unless different parts settle by different amounts.
SHEAR: (1)
The strain upon, or the failure of a structural member at a point where the
lines of force and resistance are perpendicular to the member. (2) The load
acting across a beam near its support. For a uniformly distributed load or for
any other symmetrical load, the maximum shear is equal to half the total load
on a simply supported beam, or to the total load on a cantilever beam. Maximum
shear occurs at both ends of a simply supported beam (the acting moment equal
to zero near the support's ends).
SHEATHING: A sheet metal covering over underwater timber
to protect it against marine borers; sheeting.
SHEET PILES: Closely set piles of timber, reinforced or
prestressed concrete, or steel driven vertically into the ground to keep earth
or water out of an excavation.
SHORT COLUMN: A column which is so short that if overloaded
it will fail not by crippling but by crushing.
SHOULDERS:
The portion of the roadway continguous with the traveled way for accommodation
of stopped vehicles, for emergency use and for lateral support of base and
surface courses.
SHOVING: Displacement of flexible pavement caused by
high shear stresses or because of deficient pavement material.
SHRINKAGE:
The shrinkage of concrete during hardening can amount to 0.0004 of its length
at one year or half this value at two months. Cement mortar shrinks by a
similar amount.
SHUTTERING: That part of formwork which either is in
contact with the concrete or has the form lining attached to it.
SIDEWALK: That portion of the roadway primarily
constructed for the use of pedestrians.
SILT:Grandular
material passing the No. 200 sieve (74 micron), finer than sand but coarser
than clay, such particles in the range from 2 to 50 micron. It feels gritty
between the fingers but the grains are difficult to see. It can be distinguished
from clay by the shaking test or by rolling it into a thread. A thread of silt
crumbles on drying, a clay thread does not. Rock flour and loess are materials
of silt size.
SLAB: A flat, usually horizontal cast concrete member
of uniform thickness which extends over three or more supports in a given
direction.
SLAG: The waste glass-like product from a
metallurgical furnace, which flows off above the metal.
SLAG CEMENTS:
Cements made by grinding blast-furnace slag and mixing it with lime or portland
cement or dehydrated gypsum. Slag is also used in making expanding cement and
supersulphated cement.
SLIP-FORM:
A narrow section of formwork in slab or wall shuttering that can easily be
pulled or raised as concrete in place, and is designed to be removed first,
thus making it easy to remove the remaining larger panels. It may also be
called a wrecking piece or wrecking strip.
SLUMP: The decrease in height of wet concrete when a
supporting mold is removed. It is a measure of consistency of freshly mixed
concrete.
SLURRY: A thin, watery mixture of neat cement or cement
and sand.
SOIL: Soil is gravels, sands, silts, clays, peats and
all other loose materials including topsoil, down to bedrock.
SOLDIER PILE:
An upright pile used to hold
lagging.
SOUNDNESS: Resistance to both physical and chemical
deterioration.
SPALLING: Peeling away of a surface, particularly of
portland cement concrete.
SPAN: The distance between the supports of a bridge,
truss, arch, girder, floor, beam, etc.
SPILLWAY OR
WASTEWAY: An overflow channel.
SPREAD
FOOTING: A footing used to
support a single column. This is also known as an individual column footing and
isolated footing.
SPECIFICATIONS: Written or printed description of construction work to be
done forming part of the contract, describing qualities of material and mode of
construction, and giving dimensions and other information not shown in
drawings. It includes bidding procedures, legal requirements, insurance
requirements, material and workmanship requirements, inspection and testing
procedures, and procedures for measurement and payment of the work, also the
specifications establish obligations of the contracting parties with respect to
the State (Client) and his Engineer, it is the obligation to clearly define
what is required; to establish a plan for its enforcement to the extent
required during the period of execution; and to indicate how the work will be
measured and paid for. With respect to the Contractor, it is the obligation of
complying with the Contract requirements during the construction period. The
Specifications includes Standard Specifications and Special Provisions.
SPECIAL PROVISIONS: Approved supplementary provisions, additions, revisions or
deletions to the standard specifications which may cover conditions peculiar to
an individual project.
SOIL STABILIZATION: Modification of soils or aggregates by incorporating
materials that will increase load bearing capacity, firmness and resistance to
weathering or displacement. Common methods are mixing the soil with cement or
waste oil or imported soil, also compaction or merely covering with a primer.
STANDARD
SPECIFICATIONS: The current
edition of the State's Standard Specifications for State Road and Bridge
Construction.
STANDARD
DEVIATIONS:A measure of
variability that can be calculated form the differences between individual
measurements in a group and their average.
STEADY FLOW: Flow which does not vary with time.
STRAND: A number of steel wires grouped together by
twisting.
STREET: A general term denoting a public way for
purposes of vehicular travel, including the entire area within the
right-of-way.
STRESS-ABSORBING MEMBRANE INTERLAYER (SAMI): A low-stiffness mixture of asphalt cement,
rubber and mineral aggregate placed between layers of pavement to retard the
transfer of stresses between the layers.
STRUCTURES: Bridges,
culverts, catch basins, drop inlets, retaining walls, cribbing, manholes,
headwalls, buildings, sewers, service pipes, underdrains, foundation drains and
other structural features.
STRIPPING: (1)
Loss of binder (Bituminous film) from aggregate particles or from a road
surface, due to presence of water. (2) Removing formwork. (3) Clearing a site
of turf, brush-wood, topsoil, or the first layer of soil.
SUBBASE
COURSE: One or more layers of
specified or selected materials, of designed thickness, placed on the subgrade
to support a base course.
SUBCONTRACTOR:
An individual, partnership,
firm, corporation or any acceptable combination thereof, or joint venture, to
which the contractor sublets a part of the contract.
SUBGRADE: The roadbed materials beneath the pavement
structure. The top prepared surface of the subgrade is called finished subgrade
elevation.
SUBSTRUCTURE: All that part of the bridge below the bridge seats, tops of piers,
haunches of rigid frames or below the spring lines of arches. Backwalls and
parapets of abutments and wing walls of bridges shall be considered as parts of
the substructure.
SUBSOIL: (1) The weather soil directly below the topsoil.
(2) The ground below formation level also called the subgrade or foundations.
SULPHATE-BEARING SOILS: If ground water contains more than 0.1% of SO3 or if a clay
contains more than 0.5% of SO3, high-alumina cement should be used for all
concrete in the ground. Portland pozzolana cement may sometimes give enough
protection at lower cost. No precautions needed with foundation concrete in
water containing less than 0.02% of SO3 or clay which contains less than 0.1%
of SO3.
SUMP: A pit in which water or sewage collects before
being baled or pumped out.
SUPERELEVATION: Exaggerated tilt of roadway on a curve to
counteract centrifugal force on vehicles.
SUPERSTRUCTURE: All that part of a structure above and including the
bearing of simple and continuous spans, skewbacks of arches and top of footings
of rigid frames, excluding backwalls, wingwalls, and wing protection rails.
SURETY: The corporate body bound with the contractor for
the full and complete performance of the contract and for payment of all debts
pertaining to the work.
SURCHARGE: A surface loading in addition to the soil load
behind a retaining wall.
SURFACE
RECYCLING: Recycling an
existing pavement surface by heating, scarifying (Milling), remixing,
rejuvenating with an emulsified recycling agent, placing and compacting.
SURFACE WATER: Water carried by an aggregate in addition to that held by absorption
within the aggregate particles themselves. It is water in addition to saturated
surface density water.
SURFACING: The uppermost layer of material placed on the
traveled way, or shoulders. This term is used interchangeably with pavement.
SURFACE COURSE: One or more layers of specified materials designed to
accommodate the traffic load; the top layer of which resists skidding, traffic
abrasion and the disintegrating effect of climate. The top layer is sometime
called a "wearing course".
SWELLING
PRESSURE: The pressure exerted
by a contained clay when it absorbs water. It can amount to considerably more
than the pressure of the overlying soil.
(T)
TACK COAT: A thin coat of bitumen, road tar or emulsion
laid on a road to improve the adhesion of a course above it.
TANDEM
ROLLER: A road roller having
rolls (drums) of about the same diameter behind each other on the same track.
TACK WELD: A temporary half-inch thick weld that holds
steel parts together during fabrication.
TEMPERATURE STEEL: Reinforcement which is inserted in a slab or other concrete
member to prevent cracks due to shrinkage or temperature stresses from becoming
too large. It generally amounts to a minimum of about 0.1% of the cross-section
in any direction. The requirement for a slab, which is two-dimensional, being
therefore about 0.2% altogether.
TEMPERATURE STRESS: A stress due to temperature rise or drop. If the expansion
due to temperature rise or the contraction due to temperature drop is
restrained, the member concerned is stressed in compression during rising
temperature or tension during falling temperature.
TENDON: A prestressing bar, cable, rope, strand or wire.
TERZAGHI-MEYERHOFF
EQUATION: This equation is used
to find the gross (ultimate) bearing capacity or gross pressure for a soil:
THRUST: A horizontal force, particularly the horizontal
force exerted by retained earth.
TOPSOIL: The topmost layer of the soil which by its humus
content supports vegetation. It is usually the top one foot of the soil.
TOLERANCE: Acceptable variation from a standard size.
TOUGHNESS: The resistance of a material to repeated bending
and twisting.
TORQUE,
TORSION OR TWIST: The twisting
effect of a force on a shaft applied tangentially, like the twist on a haulage
drum which winds rope on to its circumference.
TRAFFIC LANE:
That portion of a traveled way
for the movement of a single line of vehicles.
TRAVEL LANE: When
used to distinguish between passing lane and travel lane, the travel lane is
the right lane of a two lane roadway with both lanes going in the same direction.
Usually both the passing lane and the travel lane are considered travel lanes
with the passing lane considered to be the right travel lane.
TRAVELED WAY: The portion of the roadway for the movement of
vehicles exclusive of shoulders and auxiliary lanes.
TRUSS: A
frame, of steel, but also sometimes of timber, concrete, or light alloy, to
carry a roof or bridge, built up wholly from members in tension and
compression. It is generally a perfect frame or nearly so, and may be pin
jointed.
TURFING: The covering of an earth surface with growing grass cut from
another site. It can also be revetment to slopes which are usually covered by
water, made by laying turves on the slope according to a technique like sliced
blockwork.
(U)
UNIFORM FLOW:
Flow which has a constant
depth, volume and shape along its course.
UPLIFT: (1)
An upward force on earth due to water leaking into a dam or from any point
where water is under high pressure. (2) Lifting of a structure caused by: frost
heave, or on the windward side by wind force, or in a dry climate by swelling
soil.
(V)
VARRIED FLOW:
Flow that had a changing depth
along the water course. The variation is with respect to location, not time.
VIBRATED CONCRETE: Concrete consolidated by vibration from an internal or external
vibrator. It requires very much less water for effective placing than does
concrete compacted by punning, therefore it is much stronger. The formwork,
however, must also be stronger when the concrete is to be vibrated. Concrete in
hollow-tile floors is not vibrated.
VIBRATOR: A
tool which vibrates at a speed form 3,000 to 10,000 rpm and is inserted into
wet concrete or applied to the formwork to compact the concrete. Concrete
vibrators are of six types:
A) For precast
work:
(1) Platform vibrators,
small vibrators carried by one or two men moving up and down
a pile or lamp
post. (2) Table vibrators, which may vibrate vertically for heavy work or with
rotarymovement for light pieces.
B) For concrete
cast in place:
(3) Internal
vibrators are the best known type. (4) External vibrators are used more in the
factory than on the site because of the extra strength required for the
formwork. External vibrators are also used for road slabs. (5) A hand screed 12
feet long requires one vibrator, for greater lengths two vibrators
are fixed on the
screed.
C) For very
large capacities:
(6)
Concrete-vibrating machines are used.
Vibrators are
also used for the compaction of loose soils.
(W)
WARPING: Deviation of pavement surface from original
profile caused by temperature and moisture differentials.
WATER FOR
DOMESTIC USE: Potable water
used by the public (Home-use).
WORK: The
product of a force and the distance through which it moves. It is to be
distinguished from energy and from power which is a rate of doing work. Energy
can, however, be expressed in the same units as work, and often is.
WORK ON ENGINEERING CONTRACTS: Work here shall mean the furnishing of all labor,
materials, equipment and other incidentals necessary or convenient to the
sucessful completion of the project and the carrying out of all the duties and
the obligations imposed by the contract.
WEEPHOLE: A hole to allow water to escape from behind a
retaining wall and thus to reduce the pressure behind it.
WORKABILITY:
The ease with which a concrete can be mixed, placed and finished. Wet concretes
are workable but weak. Workability can be measured by the slump test, the
compacting factor test, and by the V.-B. Consistometer test.
(X)
XYLEM: The botanical name for wood.
(Y)
YIELD OR
BUCKLE: The permanent
deformation which a metal piece undergo when it is stressed beyond its elastic
limit.
(Z)
ZONING: Restrictions as to size or character of
buildings permitted within specific areas, as established by urban authorities.